BEC delivered civil, mechanical, electrical, and instrumentation works for Oman Refinery’s Diesel Hydro Desulphurisation Project. The project involved heavy lifts, piping fabrication, electrical cabling, and full instrumentation integration. Major highlights included 52 km of piping and 41 km of electrical cabling. The company’s technical precision and adherence to refinery safety standards ensured successful execution, enabling improved fuel quality production for Oman’s energy sector.
Oman Refinery Company
Oman

Complete CMEI construction for polymer flooding facilities including water treatment and polymer injection.

CMEI construction for Saih Rawl including compressor plant, power plant and 132kV transmission system.
MEI works for 585 MW Power & Desalination Plant at Sohar IWPP Phase-1.