Muscat Electricity Distribution Company S.A.O.C

Primary Substations at Wadi Kabir, Seeb, Al Khoud & Mutrah

Design and turnkey construction of 33/11kV primary substations across Muscat region.

Overview

BEC Group constructed four 33/11kV primary substations at Wadi Kabir, Seeb, Al Khoud, and Mutrah under a turnkey EPC contract. The project included detailed design, manufacturing inspection, shipment, erection, testing, commissioning, and maintenance support. The substations, each equipped with 2x20MVA transformers, were completed safely, achieving 250,000 man-hours without LTI. The team of 250 personnel delivered within the contract schedule, providing Muscat with enhanced distribution capacity and grid reliability.

Client

Muscat Electricity Distribution Company S.A.O.C

Location

Oman

Sector

Infrastructure